General Background on Temelin
(with arguments to consider)

The Loan Guarantee with the US Export Import Bank
Promises versus Reality
Time Schedule of Temelin's Construction
Costs of Temelin Project
Broken Promises about Openness to Public
Scandal around Contracts between CEZ and Westinghouse
Translation of Articles Revealing the Scandal around Westinghouse's Contract

ruler

The Loan Guarantee with the US Export Import Bank

On 10 March 1994, the U.S. Ex-Im Bank agreed to provide a $317 million loan guarantee for the construction of the Czech nuclear power plant at Temelin. The loan is taken by CEZ (Czech electricity utility) from commercial lenders and is to cover Westinghouse supplies of: a) instrumentation and control (I&C) equipment and services, b) the initial nuclear fuel.

The total contract is for $419 million, with a U.S. export value of $334 million (the rest is provided by Westinghouse Belgium). Specifically, the I&C contract has U.S. costs 243.1 million, Belgian costs $61.5 million and local costs $23.9 million. The fuel contract has U.S. costs of $90.5 million. Ex-Im Bank guarantees, including fees, total $317 million ($238.9 million for I&C plus $78.5 million for fuel).


Promises versus Reality

The Temelin project has always been controversial. Thus, the Ex-Im decision was based on many promises made to the U.S. Congress. Today, after almost 3 years, the project suffers serious cost overruns and delays; it has basically gone out of control. Many of the technical and political promises have not been met. Recently, there has been a scandal in the Czech Republic around possible bribery between CEZ and Westinghouse officials linked with their contracts. The $317 million is thus threatened.

In the light of the mentioned facts, we suggest that you commission an investigation of the Temelin project. There is still time to withdraw U.S. money (which has not yet been transfered to CEZ) from it.

Time Schedule of Temelin's Construction

In 1993, when the Czech government gave the project a green light, it was clearly stated that Temelin would be finished by the end of 1995 (first reactor) and middle of 1997 (second reactor), at a total cost of 68.8 billion CZK ($2.5 billion).

In 1994, while Czech government still confirmed the original deadline, Ex-Im wrote in its letter to Speaker of the House (January 27th, 1994) that commercial startup of the reactors was expected to happen on July 15th 1997 and October 15th 1998, respectively. This was also the time schedule based upon which Ex-Im approved its loan guarantees and calculated risks linked with them.

Since then, even Czech domestic sources have admitted several serious delays. Now, in Autumn 1996, the deadline for finishing the first Temelin reactor is the beginning of 1999. This means a delay of 3 years compared to the Czech governmental decision from 1993, and a delay of 1.5 years compared to Ex-Im promises.

Even worse, a high-positioned source within the Czech Ministry of Economy said that his office already now has studies suggesting that the first reactor will not be finished before 2000. If this happens, the overall delay will exceed 4 years.

The official explanations given by the Ministry of Economy and CEZ are worrisome, and show that recent figures are still not necessarily final. According to them, the reasons for the delays are unclarified responsibilities among suppliersm, and underestimated scope of necessary modifications, forcing unexpected necessary changes in the parts of the power plant which have already been completed (such as the need to replace several kilometers of cables with new ones, in concrete shafts so tiny that only one worker can do this job at one time).

There is a sad joke circulating among the Czech public, saying that since 1988, the start-up of Temelin is still two years away. Unfortunately, this joke has been made true for already 8 years.

Costs of Temelin Project

In 1993, when the Czech government gave the project a green light, it clearly stated that Temelin would be finished by the end of 1995 (first reactor) and mid-1997 (second reactor), both at a cost of 68.8 billion CZK ($ 2.5 billion).

...something in the range of 70 billiionSince then, the price has been raised several times, together with postponement of the construction deadlines. With the same explanations, the total price has risen by 10 billion CZK ($360 million), about the same amount as is guaranteed by Ex-Im Bank. If the Czechs did not have this money in 1994 and had to borrow it, how will they be able to cover a cost increase of the same magnitude?

Again, senior sources within Ministery of Economy claim that the internal studies which indicate a 4 year delay in project completion also estimate that the final price of the project at 100 billion CZK ($ 3.6 billion) - $ 1.1 billion more than was planned in 1993.

Broken Promises about Openness to Public

In its letter to Congressman Kennedy dated March 7, 1994, ExIm said: "As to the specific matter of public participation and access to documents, according to the Czechs, documents relating to environmental aspects of the plant are already available to the public."

We have to say that based on this Ex-Im's claim, Friends of the Earth has been requesting exactly the same documents that are listed in the attachment, but to no avail. All the responsible offices and bodies replied to our demands that they do not have these documents.

It is especially disturbing that the mentioned studies, mostly about the power plant's environmental impact, are in practice not accessible to the public. Other very important documents like the safety analysis and the documentation of modifications to the original project, which are plainly witheld from public.

Scandal around Contracts between CEZ and Westinghouse

In May 1996, the Czech media started to discover a serious scandal around three major contracts between CEZ and Westinghouse - a contract to supply a unique information system to all power plants owned by CEZ, and the two Temelin contracts - for I&C System and nuclear fuel.

What became clear was that a Westinghouse's consultant - Jan Vadlejch - was influencing the decisions inside the CEZ board of directors during the biddings for these strategic contracts.

Best documented is the first case concerning the unique information system. Allegedly, after Westinghouse won only the 3rd position in the bidding, Vadlejch arranged, by bribing some CEZ directors, to arrange a second round of bidding, where competitors got an opportunity to modify their prices. At the same time, information about other prices was leaked to Westinghouse, who then cut its price by almost 50 % in order to submit the cheapest bid. As a result, the contract was finally signed with Westinghouse.

It is worth mentioning that after managing to get the contract, Westinghouse was not able to fulfill its commitments - its supplies already are delayed by several months now.

This case is now being investigated by criminal police, and several pieces of evidence have been published - like the letter from Vadlejch to one CEZ director, that contains strategy suggestions (to announce the second round of bidding) and a promise of "fulfilling our commitments" as a return for this service.

Consequently, two other contracts - the ones for Temelin nuclear power plant - are under scrutiny. In these cases as well, evidence of bid tampering has been uncovered.

The scandal around Westinghouse's contracts has been inquired into and closely followed by the formost Czech newspaper MF DNES (Today). So far, it published over 20 major articles on this issue, many of them on its front page.

Translation of Article Revealing the Scandal around Westinghouse's Contract

ruler

Resistance | Brain Food | The Players | '97Blockade | Links | CEB | SPACE